Timetable of phases

Onboarding

S01 - 06.03.2023 - 19.03.2023

Implementation I

S02 - 20.03.2023 - 26.03.2023

S03 - 27.03.2023 - 02.04.2023

S04 - 03.04.2023 - 09.04.2023

S05 - 10.04.2023 - 16.04.2023

S06 - 17.04.2023 - 23.04.2023

Implementation II

S07 - 24.04.2023 - 30.04.2023

S08 - 01.05.2023 - 07.05.2023

S09 - 08.05.2023 - 14.05.2023

S10 - 15.05.2023 - 21.05.2023

Testing + Final changes

S11 - 22.05.2023 - 28.05.2023

S12 - 29.05.2023 - 04.06.2023

List of main tasks

  1. Implement a new method for muscle deformation based on a combination of approaches PBD and ARAP
  2. Verify behaviour on selected muscles
  3. Implement a tool to visually compare the existing approach with the new one
  4. Update / redesign the existing CMAKE system
  5. Ensure multiplatform functionality of the project
  6. Set up CI/CD mechanism on GitLab to facilitate further development
  7. Analyze and document existing time inefficiencies in implementation
  8. Optimize critical inefficiencies
Task Capacity
Communication and meetings 45 h
Documentation 50 h
*Onboarding * 30 h
*Management * 25 h
*Analysis * 60 h
Coding 320 h
Implementation 200 h
Code review 30 h
Bug fixing 50 h
Refactoring 40 h
Testing 40 h
Time reserve 30 h

Aktualizováno uživatelem Václav Šíma před asi 2 roky(ů) · 18 revizí