Wiki¶
Timetable of phases¶
Onboarding¶
S01 - 06.03.2023 - 19.03.2023
Implementation I¶
S02 - 20.03.2023 - 26.03.2023
S03 - 27.03.2023 - 02.04.2023
S04 - 03.04.2023 - 09.04.2023
S05 - 10.04.2023 - 16.04.2023
S06 - 17.04.2023 - 23.04.2023
Implementation II¶
S07 - 24.04.2023 - 30.04.2023
S08 - 01.05.2023 - 07.05.2023
S09 - 08.05.2023 - 14.05.2023
S10 - 15.05.2023 - 21.05.2023
Testing + Final changes¶
S11 - 22.05.2023 - 28.05.2023
S12 - 29.05.2023 - 04.06.2023
List of main tasks¶
- Implement a new method for muscle deformation based on a combination of approaches PBD and ARAP
- Verify behaviour on selected muscles
- Implement a tool to visually compare the existing approach with the new one
- Update / redesign the existing CMAKE system
- Ensure multiplatform functionality of the project
- Set up CI/CD mechanism on GitLab to facilitate further development
- Analyze and document existing time inefficiencies in implementation
- Optimize critical inefficiencies
Task | Capacity |
Communication and meetings | 45 h |
Documentation | 50 h |
Onboarding | 30 h |
Management | 25 h |
Analysis | 60 h |
Coding | 320 h |
Implementation | 200 h |
Code review | 30 h |
Bug fixing | 50 h |
Refactoring | 40 h |
Testing | 40 h |
Time reserve | 30 h |