Timetable of phases

Onboarding

S01 - 06.03.2023 - 19.03.2023

Implementation I

S02 - 20.03.2023 - 26.03.2023

S03 - 27.03.2023 - 02.04.2023

S04 - 03.04.2023 - 09.04.2023

S05 - 10.04.2023 - 16.04.2023

S06 - 17.04.2023 - 23.04.2023

Implementation II

S07 - 24.04.2023 - 30.04.2023

S08 - 01.05.2023 - 07.05.2023

S09 - 08.05.2023 - 14.05.2023

S10 - 15.05.2023 - 21.05.2023

Testing + Final changes

S11 - 22.05.2023 - 28.05.2023

S12 - 29.05.2023 - 04.06.2023

List of main tasks

  1. Implement a new method for muscle deformation based on a combination of approaches PBD and ARAP
  2. Verify behaviour on selected muscles
  3. Implement a tool to visually compare the existing approach with the new one
  4. Update / redesign the existing CMAKE system
  5. Ensure multiplatform functionality of the project
  6. Set up CI/CD mechanism on GitLab to facilitate further development
  7. Analyze and document existing time inefficiencies in implementation
  8. Optimize critical inefficiencies
Task Capacity
Communication and meetings 45 h
Documentation 50 h
Onboarding
Management
Analysis
Coding

45h

50h

30h

25h

60h

320h
Implementation
200h
Code review
30h
Bug fixing
50h
Refactoring
40h
Testing
40h
Time reserve
30h