Project plan¶
Plan for project implementation
!Due to the departure of a team member, a new plan had to be drawn up. - New_plan !¶
Onboarding¶
S01 - 06.03.2023 - 19.03.2023- Getting acquainted with new technologies, collecting information from the client and creation of strategic plan.
- - Scope concurrence: done
- - Initial requirements definition: done
- - Plan concurrence: done
- - Risk acceptance: done
- - Process acceptance: done
- - Feasibility: done
- - Project plan: done
- Achievement of LCO milestone
Implementation I - New method for muscle deformation¶
- Achievement of LCA milestone
- S02 - 20.03.2023 - 26.03.2023 - Obtaining a more detailed specification from the client and beginning the analysis of the existing solution.
- S03 - 27.03.2023 - 02.04.2023 - Final specification of requirements, completion of solution analysis and start of implementation. Familiarisation with CI/CD.
- S04 - 03.04.2023 - 09.04.2023 - Completion of the super build, presentation of the design solution to the client. If everything goes smoothly start with the testing proposal.
- S05 - 10.04.2023 - 16.04.2023 - Completion of implementation of merging methods, correction of deficiencies in consultation with the client, testing.
Implementation II - Tool for comparision¶
- Achievement of IOC milestone
- S06 - 17.04.2023 - 23.04.2023 - Completion of deficiencies from the previous phase. Start of analysis of methods to compare results.
- S07 - 24.04.2023 - 30.04.2023 - Proceeding with the analysis, consultation with the client, initial design and architecture of the method.
- S08 - 01.05.2023 - 07.05.2023 - Design completion and start of method implementation.
- S09 - 08.05.2023 - 14.05.2023 - Implementation (GUI merge - Probably time consuming we need to decompose before the start of the phase.)
- S10 - 15.05.2023 - 21.05.2023 - Completion of the implementation part, bug fixing and start of testing
Testing + Final changes¶
- Achievement of GA milestone
- S11 + S12 - 22.05.2023 - 04.06.2023 - Final testing, writing up the outputs we have achieved, time reserve.
Estimations of categories¶
Task Capacity Total avalible capacity 600 h -- -- Communication and meetings 45 h Documentation 50 h Onboarding 30 h Management 25 h Analysis 60 h Coding 320 h - Implementation 200 h - Code review 30 h - Bug fixing 50 h - Refactoring 40 h Testing 40 h Time reserve 30 h
Summary of requirements¶
- Implement a new method for muscle deformation based on a combination of approaches PBD and ARAP
- Verify behaviour on selected muscles
- Implement a tool to visually compare the existing approach with the new one
- Update / redesign the existing CMAKE system
- Ensure multiplatform functionality of the project
- Set up CI/CD mechanism on GitLab to facilitate further development
- Analyze and document existing time inefficiencies in implementation
- Optimize critical inefficiencies
Gantt Chart¶