Project plan

Plan for project implementation

Onboarding

S01 - 06.03.2023 - 19.03.2023
  • Getting acquainted with new technologies, collecting information from the client and creation of strategic plan.
  • - Scope concurrence: done
  • - Initial requirements definition: done
  • - Plan concurrence: done
  • - Risk acceptance: done
  • - Process acceptance: done
  • - Feasibility: done
  • - Project plan: done
  • Achievement of LCO milestone

Implementation I - New method for muscle deformation

  • Achievement of LCA milestone
  • S02 - 20.03.2023 - 26.03.2023 - Obtaining a more detailed specification from the client and beginning the analysis of the existing solution.
  • S03 - 27.03.2023 - 02.04.2023 - Final specification of requirements, completion of solution analysis and start of implementation. Familiarisation with CI/CD.
  • S04 - 03.04.2023 - 09.04.2023 - Completion of the super build, presentation of the design solution to the client. If everything goes smoothly start with the testing proposal.
  • S05 - 10.04.2023 - 16.04.2023 - Completion of implementation of merging methods, correction of deficiencies in consultation with the client, testing.

Implementation II - Tool for comparision

  • Achievement of IOC milestone
  • S06 - 17.04.2023 - 23.04.2023 - Completion of deficiencies from the previous phase. Start of analysis of methods to compare results.
  • S07 - 24.04.2023 - 30.04.2023 - Proceeding with the analysis, consultation with the client, initial design and architecture of the method.
  • S08 - 01.05.2023 - 07.05.2023 - Design completion and start of method implementation.
  • S09 - 08.05.2023 - 14.05.2023 - Implementation (GUI merge - Probably time consuming we need to decompose before the start of the phase.)
  • S10 - 15.05.2023 - 21.05.2023 - Completion of the implementation part, bug fixing and start of testing

Testing + Final changes

  • Achievement of GA milestone
  • S11 + S12 - 22.05.2023 - 04.06.2023 - Final testing, writing up the outputs we have achieved, time reserve.

Estimations of categories

Task Capacity
Total avalible capacity 600 h
-- --
Communication and meetings 45 h
Documentation 50 h
Onboarding 30 h
Management 25 h
Analysis 60 h
Coding 320 h
- Implementation 200 h
- Code review 30 h
- Bug fixing 50 h
- Refactoring 40 h
Testing 40 h
Time reserve 30 h

Summary of requirements

  1. Implement a new method for muscle deformation based on a combination of approaches PBD and ARAP
  2. Verify behaviour on selected muscles
  3. Implement a tool to visually compare the existing approach with the new one
  4. Update / redesign the existing CMAKE system
  5. Ensure multiplatform functionality of the project
  6. Set up CI/CD mechanism on GitLab to facilitate further development
  7. Analyze and document existing time inefficiencies in implementation
  8. Optimize critical inefficiencies

Gantt Chart