h1. Planning
h2. Timetable of phases
h3. Onboarding
S01 - 06.03.2023 - 19.03.2023
* Getting acquainted with new technologies, collecting information from the client and creation of strategic plan.
* - Scope concurrence: done
* - Initial requirements definition: done
* - Plan concurrence: done
* - Risk acceptance: done
* - Process acceptance: done
* - Feasibility: done
* - Project plan: done
* *Achievement of LCO milestone*
h3. Implementation I
* *Achievement of LCA milestone*
S02 - 20.03.2023 - 26.03.2023
S03 - 27.03.2023 - 02.04.2023
S04 - 03.04.2023 - 09.04.2023
S05 - 10.04.2023 - 16.04.2023
S06 - 17.04.2023 - 23.04.2023
h3. Implementation II
* *Achievement of IOC milestone*
S07 - 24.04.2023 - 30.04.2023
S08 - 01.05.2023 - 07.05.2023
S09 - 08.05.2023 - 14.05.2023
S10 - 15.05.2023 - 21.05.2023
h3. Testing + Final changes
* *Achievement of GA milestone*
S11 - 22.05.2023 - 28.05.2023
S12 - 29.05.2023 - 04.06.2023
h2. Estimations of categories
> | *Task* | *Capacity* |
> | *Communication and meetings* | 45 h|
> | *Documentation* | 50 h |
> | *Onboarding* | 30 h |
> | *Management* | 25 h |
> | *Analysis* | 60 h |
> | *Coding* | 320 h |
> |- Implementation| 200 h |
> |- Code review| 30 h |
> |- Bug fixing| 50 h |
> |- Refactoring| 40 h |
> | *Testing* | 40 h |
> | *Time reserve* | 30 h |
h2. Functional requirements
# Implement a new method for muscle deformation based on a combination of approaches PBD and ARAP
# Verify behaviour on selected muscles
# Implement a tool to visually compare the existing approach with the new one
# Update / redesign the existing CMAKE system
# Ensure multiplatform functionality of the project
# Set up CI/CD mechanism on GitLab to facilitate further development
# Analyze and document existing time inefficiencies in implementation
# Optimize critical inefficiencies
h2. Gantt Chart
!ganttt.png!