Iterations

Summary of project work in interations.

S01 ( 06.03.2023 - 19.03.2023 )

  • selection of a suitable IDE - Visual Studio
  • specification of requirements
  • agreement that everyone has to learn c++ (nobody knows c++)
  • introduction to cMake
  • gitflow settings
  • setting meeting times (Saturday 9:00 (planning + retrospective) + Wednesday 17:00)

S02 ( 20.03.2023 - 26.03.2023 )

  • getting the program up and running
  • source code analysis
  • workshop with the client about cMake and project requirements
  • creation of a project plan
  • configuration of Redmine and setting conventions

Retrospective

GLAD:
  • TK - Vasek made a nice plan
  • TK - Compared to the previous sprint we are more coordinated, more efficient
  • MJ - Better planning
  • JK - Clarifying the procedure with the mentor
SAD:
  • TK - I don't really understand the code
  • JK - The code is complicated
MAD:
  • VŠ - we are a little behind schedule
  • VŠ - we need to correctly specify the requirements for each task (optimizing is not a sufficient description)

S03 ( 27.03.2023 - 02.04.2023 )

  • workshop with the client about mathematical background of the project and source code structure
  • risk analysis document prepared
  • vision document prepared
  • source code analysis of ARAP and PBD

Retrospective

GLAD:
  • JK - the meeting with the author of the project was very useful
  • TK - the meeting with the author helped me to get a better understanding of the code
  • VŠ - the meeting with the author was good
  • VŠ - we made up for the initial delay in the plan
  • TK - Vasek played nicely with the administration
SAD:
  • TK - I analyzed a lot of things, but I still don't feel like I have a proper understanding of how everything works
  • JK - lots of work, little time
  • VŠ - Mathematically challenging project, big overhead for analysis
  • VŠ - We will descope cMake refactoring to the next sprint
MAD:
  • VŠ - We still have a big slippage, we should escalate the situation better
  • VŠ - Tomas writes Czech in Redmine
  • VŠ - We need to improve communication in the team, we don't have a very good overview of the status of the individual tasks

S04 ( 03.04.2023 - 09.04.2023 )

  • consultations with client about PBD and ARAP merge
  • architecture document first part prepared
  • internal convention document prepared
  • resolving super-build issue

Retrospective

GLAD:
  • JK - better understanding of the mathematical part of the method
SAD:
  • JK - a team member couldn't handle the time pressure
  • JK - high mental load
MAD:
  • TK - MJ left us
  • VŠ - basically zero progress on Cmake, I started implementing from scratch
  • VŠ - missing team member + delay on cMake will make big problems for on-time delivery

S05 ( 10.04.2023 - 16.04.2023 )

  • Setting new targets - removing a task for comparison of results
  • Testing is unlikely to be as high quality due to time constraints

Retrospective

GLAD:
  • TK - The client is helpful and supportive
  • VŠ - We have the first implementation deliverable
  • VŠ - Improved team communication
  • VŠ - Moving the meeting to Sunday evening is better for closing tickets
  • TK - I better understand the connection of building c++ projects (Cmake etc.)
  • JK - positive feedbakc from ASWI mentor
  • TK - Vasek made nice documents => lots of points on ASWI evaluation
  • VŠ - team morale is not dropping (probably could now be less now)
SAD:
  • JK - Mental state remains unchanged
  • VĚ - Every step of putting together a project results in a problem that blocks development
MAD:
  • TK - I'm already on my second week of almost 0% progress and it's severely demoralizing (despite X hours spent on the task)

Actionable points

  • Trying to get the project to a state where we can start implementing as soon as possible
  • Help from the author + focus on the build process
  • Lunch together to boost team morale
  • Incorporate deadlines from other coursework into deadline planning

S06 ( 17.04.2023 - 23.04.2023 )

  • oSim superbuild is working now on Win
  • Fixing an unexpected bug that was in our project
  • ARAP method - the project is in a state where we can address the combination of both methods
  • We have received from the project author his proposal for a solution to the combination of methods

Retrospective

GLAD:
  • JK - quite a lot of implementation progress
  • JK - having lunch with the team was beneficial, I got motivated to continue my studies
  • TK - finally something is working -> big boost to morale
  • TK - Client satisfied with our bug fix
  • VŠ - One big feature was descoped, according to our new plan, we should be able to delivery everything on time
SAD:
  • JK - time pres from other subjects
  • TK - I'm scared that we won't be able to get everything done in time
  • VŠ - In superbuild there is often a problem with external libraries (can't be translated, not compatible, other problems) - this creates blockers that prevent further progress and are time-consuming to resolve (hard to estimate time to resolve these kind of problems)
MAD:
  • TK - I managed to forget about half of the mathematical background

Previous actionable points outcomes

  • Project is now in runnable state - perfect
  • Lunch together to boost team morale was good

Actionable points

  • Create a prototype of the combination of PBD & ARAP methods
  • Implement at least one of the two possible combinations (using scales or using a combination of kinetic forces)
  • Would be helpufull to have one GIT repo for both features, current situation might lead in merge issues