h1. Retrospective and planning after iteration 3 

 *Date:* 09.04. 2021, 15:00 
 *Present:* Jan Pašek, Michal Seják, Stanislav Král, David Friesecký 

 h2. Agenda 

 # Each of the team briefly evaluates the pros and cons of the iteration based on the following points: project state, project plan, team cooperation, tools, artefacts 
 # What shall be better in the next iteration? 
 # How did we managed to change problematic points from the previous retrospective? 
 # Other problems  
 # Evaluate if we achieved the iteration targets 
 # Synchronization discussion (short standup) 
 # Planning of the next iteration 

 

 h2. Conclusion 

 # Evaluation of the iteration: 

  * Honza: Targets were met, software architecture was built from scratch which was exhausting work. 

  * David: Estimations shall be improved for the future, but it shall be better next time. The rest of the work was OK. 

  * Michal: Best iteration, joyful tasks. No other comments. 

  * Standa: Big overshoots of the task estimations. Architecture is implemented and ready to be extended. 
 # Review process shall be improved. Maybe a walk-through review can be done. 
 # Estimations shall be significantly better. 